Power grid material storage management system
1. A power grid material reserve management system, comprising:
the first-level unit declaration module is used for receiving a first-level material purchasing request sent by a city-level demand end; the first-level material purchasing request comprises first-level engineering project information and first-level purchasing information;
the primary unit examination module is used for examining the primary material purchasing request, carrying out primary demand balance interest bank examination aiming at the primary purchasing information and forming a new primary material purchasing request; the system also comprises a purchasing mode used for checking first-level purchasing information in a new first-level material purchasing request, wherein when the purchasing mode is single-source purchasing or batch purchasing, the system sends the new first-level material purchasing request to a higher-level checking module, when the purchasing mode is authorized entrusting purchasing, the system sends the new first-level material purchasing request to a bid inviting purchasing module, and when the purchasing mode is protocol inventory purchasing, the system sends the new first-level material purchasing request to a protocol inventory checking module; the system is also used for examining a new secondary material purchasing request, and performing primary demand balance profit bank examination on secondary purchasing information of the new secondary material purchasing request to form a secondary balanced material purchasing request; the system is also used for checking whether the purchasing mode of the secondary purchasing information in the secondary balancing material purchasing request is protocol inventory purchasing, if so, sending the secondary balancing material purchasing request to the protocol inventory checking module, and if not, sending the secondary balancing material purchasing request to the superior checking module;
the secondary unit declaration module is used for receiving a secondary material purchasing request sent by a county-level demand end; the second-level material purchasing request comprises second-level engineering project information and second-level purchasing information;
the secondary unit examination module is used for examining the secondary material purchasing request, carrying out secondary demand balance interest bank examination aiming at the secondary purchasing information and forming a new secondary material purchasing request; the system also comprises a purchasing mode used for checking the secondary purchasing information in the new secondary material purchasing request, wherein when the purchasing mode is single-source purchasing or batch purchasing, the system sends the new secondary material purchasing request to the primary checking module, when the purchasing mode is authorized entrusting purchasing, the system sends the new secondary material purchasing request to the bid inviting purchasing module, and when the purchasing mode is agreement inventory purchasing, the system sends the new secondary material purchasing request to the primary checking module;
the upper examination module is used for examining a new primary material purchasing request and a secondary balance material purchasing request, examining and passing financial budgets and generating purchasing data;
the agreement inventory examination module is used for examining a new primary material purchasing request and a secondary balance material purchasing request and generating purchasing data after the examination is passed;
and the bid procurement module is used for examining the new primary material procurement request and the new secondary material procurement request and generating procurement data after the examination is passed.
2. The power grid material reserve management system according to claim 1, further comprising a first-level unit reserve plan review module for reviewing a first-level unit reserve plan sent by a market-level demand end, and sending review qualification information to the market-level demand end after the review is passed; the city-level demand end sends a first-level material purchasing request to a first-level unit declaration module based on a first-level unit reserve plan; the primary unit reserve plan comprises a project material inventory and a technical specification corresponding to the primary unit project.
3. The system of claim 2, wherein the primary unit reserve plan review module comprises:
the rule checking library is used for storing information integrity rules, purchasing information standard rules and technical standard rules;
and the primary unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the primary unit for information integrity, purchasing information standardization and technical compliance, sending examination qualified information to the market-level demand end if the examination is passed, and sending examination unqualified information to the market-level demand end if the examination is not passed.
4. The system according to claim 1, wherein the primary unit audit module comprises:
the primary demand balance interest bank examination unit is used for examining the primary material purchasing request, carrying out primary demand balance interest bank examination according to primary purchasing information, examining the material reserve quantity in the primary unit reserve resource pool, determining the actual engineering project required quantity and forming a new primary material purchasing request; the system is also used for examining a new secondary material purchasing request, performing primary demand balance profit bank examination on secondary purchasing information of the new secondary material purchasing request, checking the material reserve quantity in a secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a secondary balance material purchasing request;
the first-level purchasing mode examining unit is used for examining the purchasing mode of first-level purchasing information in a new first-level material purchasing request, sending the new first-level material purchasing request to the higher-level examining module when the purchasing mode is single-source purchasing or batch purchasing, sending the new first-level material purchasing request to the bid inviting purchasing module when the purchasing mode is authorized entrusting purchasing, and sending the new first-level material purchasing request to the agreement inventory examining module when the purchasing mode is agreement inventory purchasing; and the system is also used for checking whether the purchasing mode of the secondary purchasing information in the secondary balance material purchasing request is protocol inventory purchasing, if so, sending the secondary balance material purchasing request to the protocol inventory checking module, and if not, sending the secondary balance material purchasing request to the superior checking module.
5. The system according to claim 4, wherein the primary unit audit module further comprises: the primary unit demand unit is used for detecting whether the purchasing mode in the primary purchasing information is protocol stock purchasing or not when the primary unit examination module receives the primary material purchasing request, merging the material demand quantity belonging to the protocol stock purchasing if the purchasing mode in the primary purchasing information is the protocol stock purchasing, and not merging if the purchasing mode in the primary purchasing information is the protocol stock purchasing; and then sending the combined primary material purchasing request or the uncombined primary material purchasing request to a primary demand balance interest bank examination unit.
6. The power grid material reserve management system according to claim 1, further comprising a secondary unit reserve plan review module for reviewing a secondary unit reserve plan sent by a county-level demand terminal, and sending review qualified information to the county-level demand terminal after the review is passed; the county-level demand end sends a secondary material purchasing request to a secondary unit declaration module based on a secondary unit storage plan; the secondary unit reserve plan comprises a project material inventory and a technical specification corresponding to the secondary unit project.
7. The system of claim 6, wherein the secondary unit reserve plan review module comprises:
the rule checking library is used for storing information integrity rules, purchasing information standard rules and technical standard rules;
and the secondary unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the secondary unit for information integrity, purchasing information standardization and technical compliance, sending examination qualified information to the county-level demand end if the examination is passed, and sending examination unqualified information to the county-level demand end if the examination is not passed.
8. The system according to claim 1, wherein the secondary unit audit module comprises:
the secondary demand balance interest bank examination unit is used for examining the secondary material purchasing request, carrying out secondary demand balance interest bank examination according to secondary purchasing information, checking the material reserve quantity in a secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a new secondary material purchasing request;
and the secondary purchasing mode auditing unit is used for auditing the purchasing mode of secondary purchasing information in the new secondary material purchasing request, transmitting the new secondary material purchasing request to the primary auditing module when the purchasing mode is single-source purchasing or batch purchasing, transmitting the new secondary material purchasing request to the bidding purchasing module when the purchasing mode is authorized entrusting purchasing, and transmitting the new secondary material purchasing request to the primary auditing module when the purchasing mode is agreement inventory purchasing.
9. The system according to claim 8, wherein the secondary unit audit module further comprises: the second-level unit demand unit is used for detecting whether the purchase mode in the second-level purchase information is protocol inventory purchase or not when a second-level material purchase request is received, merging the material demand quantity belonging to the protocol inventory purchase if the purchase mode in the second-level purchase information is the protocol inventory purchase, and not merging the material demand quantity if the purchase mode in the second-level purchase information is the protocol inventory purchase; and then sending the combined secondary material purchasing request or the uncombined secondary material purchasing request to a secondary demand balance interest bank examination unit.
10. The system according to claim 1, wherein the agreement inventory audit module comprises:
the protocol inventory checking unit is used for synchronizing a protocol inventory plan of the ERP system and synchronizing protocol inventory data;
the agreement inventory examination unit is used for examining a new primary material purchase request and a secondary balance material purchase request, generating purchase data after examination is passed, and returning the examination data to the primary unit examination module after the examination is not passed;
the agreement inventory checking unit is carried out before the agreement inventory checking unit checks the first-level material purchasing request and the second-level balancing material purchasing request.
Background
In a planned reporting power grid material inspection stage, functions of ERP and ECP are insufficient in a planned inspection part, material plan inspection of prefectures and counties companies is carried out on line, and data errors or omissions can be caused due to the fact that online interaction and offline interaction exist. In addition, at present, the resource information such as stock backlog materials and the like is scattered, and manual statistics is adopted at present without classification. In project construction, the timeliness requirement on material supply is extremely high, and the actual requirement cannot be met by the existing offline manual matching mode.
The invention patent application CN202010418616.6 discloses an inventory matching system based on automatic management, and particularly discloses a system based on an EPR system for establishing an intelligent balance interest library of inventory materials; the business architecture of the intelligent balance interest bank of the stock materials comprises a resource overall resource pool, intelligent matching and result execution of the interest bank. The invention establishes an inventory material resource pool, classifies the materials in the resource pool, establishes a county, city and province three-level balance interest library mechanism, brings unallocated agreement inventory share and materials left in the library into the overall inventory resource planning management range of the whole province, assists in decision making to judge whether the demand plan needs to execute balance interest library, accelerates material turnover and reduces capital cost; and intelligent matching analysis interest library suggestions are set according to different requirement levels, so that the aims of improving supply timeliness and pressure drop inventory and creating a good operator environment are fulfilled. The method comprises the steps of firstly carrying out requirement matching within the range of the unit factory, if the item is not met or only a part of requirements are met, continuing to select the secondary range for matching, and if the resources in the secondary range are not met, carrying out requirement matching within the tertiary range, and if the resources in the tertiary range are not met, directly purchasing the part which is not met. The invention performs demand distribution from the balance profit bank perspective, but does not form a set of comprehensive system for demand balance distribution and purchase examination, and can not reasonably examine the purchase demands of all levels of materials.
Disclosure of Invention
Aiming at the problems in the prior art, the invention provides a power grid material storage management system, which can reduce the data statistics workload in the material plan management work, can reasonably plan and examine the purchasing demands at all levels, and has high material storage management efficiency.
The invention is realized by the following technical scheme:
a power grid material reserve management system, comprising:
the first-level unit declaration module is used for receiving a first-level material purchasing request sent by a city-level demand end; the first-level material purchasing request comprises first-level engineering project information and first-level purchasing information;
the primary unit examination module is used for examining the primary material purchasing request, carrying out primary demand balance interest bank examination aiming at the primary purchasing information and forming a new primary material purchasing request; the system also comprises a purchasing mode used for checking first-level purchasing information in a new first-level material purchasing request, wherein when the purchasing mode is single-source purchasing or batch purchasing, the system sends the new first-level material purchasing request to a higher-level checking module, when the purchasing mode is authorized entrusting purchasing, the system sends the new first-level material purchasing request to a bid inviting purchasing module, and when the purchasing mode is protocol inventory purchasing, the system sends the new first-level material purchasing request to a protocol inventory checking module; the system is also used for examining a new secondary material purchasing request, and performing primary demand balance profit bank examination on secondary purchasing information of the new secondary material purchasing request to form a secondary balanced material purchasing request; the system is also used for checking whether the purchasing mode of the secondary purchasing information in the secondary balancing material purchasing request is protocol inventory purchasing, if so, sending the secondary balancing material purchasing request to the protocol inventory checking module, and if not, sending the secondary balancing material purchasing request to the superior checking module;
the secondary unit declaration module is used for receiving a secondary material purchasing request sent by a county-level demand end; the second-level material purchasing request comprises second-level engineering project information and second-level purchasing information;
the secondary unit examination module is used for examining the secondary material purchasing request, carrying out secondary demand balance interest bank examination aiming at the secondary purchasing information and forming a new secondary material purchasing request; the system also comprises a purchasing mode used for checking the secondary purchasing information in the new secondary material purchasing request, wherein when the purchasing mode is single-source purchasing or batch purchasing, the system sends the new secondary material purchasing request to the primary checking module, when the purchasing mode is authorized entrusting purchasing, the system sends the new secondary material purchasing request to the bid inviting purchasing module, and when the purchasing mode is agreement inventory purchasing, the system sends the new secondary material purchasing request to the primary checking module;
the upper examination module is used for examining a new primary material purchasing request and a secondary balance material purchasing request, examining and passing financial budgets and generating purchasing data;
the agreement inventory examination module is used for examining a new primary material purchasing request and a secondary balance material purchasing request and generating purchasing data after the examination is passed;
and the bid procurement module is used for examining the new primary material procurement request and the new secondary material procurement request and generating procurement data after the examination is passed.
The system is constructed on a power grid cloud, and a distributed service architecture is adopted. The distributed service architecture comprises a distributed service layer and a data layer, and is connected with county, city and province three-level systems (ERP and ECP systems) through interfaces to realize the reporting and examination of purchasing demands of three-level material departments, and balances the purchasing demands by using a balance interest base in the reporting process, so that the problems of asymmetric information and tedious manual statistics of all levels of systems are solved.
The system can reasonably plan and examine the purchasing requirements of all levels, the county-level purchasing request declaration needs to be examined sequentially through county-level interior, city-level and provincial levels, and the city-level purchasing request declaration needs to be examined sequentially through city-level interior and provincial levels. In the checking process, different purchasing requirements are checked for different purchasing modes, and the purchasing request checking efficiency is improved.
Preferably, the system also comprises a first-level unit reserve plan examination module, which is used for examining a first-level unit reserve plan sent by the market-level demand end and sending examination qualified information to the market-level demand end after the examination is passed; the city-level demand end sends a first-level material purchasing request to a first-level unit declaration module based on a first-level unit reserve plan; the primary unit reserve plan comprises a project material inventory and a technical specification corresponding to the primary unit project.
Preferably, the primary unit reserve plan reviewing module comprises:
the rule checking library is used for storing information integrity rules, purchasing information standard rules and technical standard rules;
and the primary unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the primary unit for information integrity, purchasing information standardization and technical compliance, sending examination qualified information to the market-level demand end if the examination is passed, and sending examination unqualified information to the market-level demand end if the examination is not passed.
Preferably, the primary unit examination module includes:
the primary demand balance interest bank examination unit is used for examining the primary material purchasing request, carrying out primary demand balance interest bank examination according to primary purchasing information, examining the material reserve quantity in the primary unit reserve resource pool, determining the actual engineering project required quantity and forming a new primary material purchasing request; the system is also used for examining a new secondary material purchasing request, performing primary demand balance profit bank examination on secondary purchasing information of the new secondary material purchasing request, checking the material reserve quantity in a secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a secondary balance material purchasing request;
the first-level purchasing mode examining unit is used for examining the purchasing mode of first-level purchasing information in a new first-level material purchasing request, sending the new first-level material purchasing request to the higher-level examining module when the purchasing mode is single-source purchasing or batch purchasing, sending the new first-level material purchasing request to the bid inviting purchasing module when the purchasing mode is authorized entrusting purchasing, and sending the new first-level material purchasing request to the agreement inventory examining module when the purchasing mode is agreement inventory purchasing; and the system is also used for checking whether the purchasing mode of the secondary purchasing information in the secondary balance material purchasing request is protocol inventory purchasing, if so, sending the secondary balance material purchasing request to the protocol inventory checking module, and if not, sending the secondary balance material purchasing request to the superior checking module.
Preferably, the primary unit examination module further includes: the primary unit demand unit is used for detecting whether the purchasing mode in the primary purchasing information is protocol stock purchasing or not when the primary unit examination module receives the primary material purchasing request, merging the material demand quantity belonging to the protocol stock purchasing if the purchasing mode in the primary purchasing information is the protocol stock purchasing, and not merging if the purchasing mode in the primary purchasing information is the protocol stock purchasing; and then sending the combined primary material purchasing request or the uncombined primary material purchasing request to a primary demand balance interest bank examination unit.
Preferably, the system also comprises a secondary unit reserve plan examination module, which is used for examining a secondary unit reserve plan sent by the county-level demand end and sending examination qualified information to the county-level demand end after the examination is passed; the county-level demand end sends a secondary material purchasing request to a secondary unit declaration module based on a secondary unit storage plan; the secondary unit reserve plan comprises a project material inventory and a technical specification corresponding to the secondary unit project.
Preferably, the secondary unit reserve plan review module comprises:
the rule checking library is used for storing information integrity rules, purchasing information standard rules and technical standard rules;
and the secondary unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the secondary unit for information integrity, purchasing information standardization and technical compliance, sending examination qualified information to the county-level demand end if the examination is passed, and sending examination unqualified information to the county-level demand end if the examination is not passed.
Preferably, the secondary unit review module comprises:
the secondary demand balance interest bank examination unit is used for examining the secondary material purchasing request, carrying out secondary demand balance interest bank examination according to secondary purchasing information, checking the material reserve quantity in a secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a new secondary material purchasing request;
and the secondary purchasing mode auditing unit is used for auditing the purchasing mode of secondary purchasing information in the new secondary material purchasing request, transmitting the new secondary material purchasing request to the primary auditing module when the purchasing mode is single-source purchasing or batch purchasing, transmitting the new secondary material purchasing request to the bidding purchasing module when the purchasing mode is authorized entrusting purchasing, and transmitting the new secondary material purchasing request to the primary auditing module when the purchasing mode is agreement inventory purchasing.
Preferably, the secondary unit review module further comprises: the second-level unit demand unit is used for detecting whether the purchase mode in the second-level purchase information is protocol inventory purchase or not when a second-level material purchase request is received, merging the material demand quantity belonging to the protocol inventory purchase if the purchase mode in the second-level purchase information is the protocol inventory purchase, and not merging the material demand quantity if the purchase mode in the second-level purchase information is the protocol inventory purchase; and then sending the combined secondary material purchasing request or the uncombined secondary material purchasing request to a secondary demand balance interest bank examination unit.
Preferably, the agreement inventory review module includes:
the protocol inventory checking unit is used for synchronizing a protocol inventory plan of the ERP system and synchronizing protocol inventory data;
the agreement inventory examination unit is used for examining a new primary material purchase request and a secondary balance material purchase request, generating purchase data after examination is passed, and returning the examination data to the primary unit examination module after the examination is not passed;
the agreement inventory checking unit is carried out before the agreement inventory checking unit checks the first-level material purchasing request and the second-level balancing material purchasing request.
The invention has the following beneficial effects:
a power grid material storage management system can reasonably plan and inspect purchasing requirements of all levels, balance the purchasing requirements by utilizing a balance interest bank in the inspection process, optimize balance material storage and purchasing requirements and improve material storage management efficiency.
Drawings
Fig. 1 is a system structure block diagram of a power grid material reserve management system according to the present invention;
FIG. 2 is a flow chart of material procurement request declaration by a first-level unit, which mainly refers to a city-level unit (including a directly subordinate unit);
fig. 3 is a flow chart of material procurement request declaration in a secondary unit, which mainly refers to a county-level unit.
Detailed Description
The following are specific embodiments of the present invention and are further described with reference to the drawings, but the present invention is not limited to these embodiments.
The invention relates to a power grid material reporting system which is realized based on a power grid cloud, wherein the power grid cloud adopts a distributed service architecture and comprises a distributed service layer and a data layer. The distributed service layer supports services of different service types and is divided into end processing services and non-end processing services. The end processing service deals with power grid out-of-cloud access, and different access modes correspond to different end processing services, such as a browser end accessing corresponding WEB end processing service and a desktop end accessing corresponding desktop end processing service. The end-processing service may invoke any non-end-processing service. The non-end processing services may invoke each other. The distributed service architecture is a distributed micro-service architecture and comprises a plurality of micro applications and micro services, project application examples are deployed on an ECS application server and integrated with a related service system through an interface, and data are integrated to an RDS database from an ODPS to realize data query and analysis.
The system of the invention utilizes the framework to construct a power grid material storage management system. Referring to fig. 1, the power grid material storage management system of the present invention includes a primary unit reporting module, a primary unit reviewing module, a secondary unit reporting module, a secondary unit reviewing module, a superior reviewing module, a protocol inventory reviewing module, and a bid procurement module. The first-level unit declaration module is used for receiving a first-level material purchasing request sent by a city-level demand end. The first-level material purchasing request comprises first-level engineering project information and first-level purchasing information. And the secondary unit declaration module is used for receiving a secondary material purchasing request sent by a county-level demand end. The second-level material purchasing request comprises second-level engineering project information and second-level purchasing information. The first-level engineering project and the second-level engineering project correspond to the engineering project of a first-level unit and the engineering project of a second-level unit respectively. The engineering projects all comprise engineering project names, such as 220kv design projects of a certain road section in Zhejiang province, and 110kv design projects of a certain road section in Huzhou city. The first-level purchasing information and the second-level purchasing information respectively correspond to purchasing information of a first-level unit and purchasing information of a second-level unit. The purchase information comprises purchase price, purchase mode, purchase category, purchase quantity, material information, technical specification ID and purchase price. And the purchasing information is determined according to the project material inventory information. The purchasing mode comprises national network agreement inventory, network province agreement inventory, national network centralized tender purchasing, network province centralized tender purchasing, single source purchasing and authorized purchasing. The purchasing category comprises equipment, materials, services, ownership, electric energy meter special items and the like. The first-level unit examination module examines a first-level material purchasing request sent by the first-level unit reporting module, a balance profit bank and a purchasing mode examination are sequentially carried out, and related requests are sent to a higher-level examination module, a bid inviting purchasing module and a protocol inventory examination module at a provincial-level demand end to carry out targeted purchasing examination according to the purchasing mode (see figure 2). The second-level unit examination module examines a second-level material purchasing request sent by the second-level unit declaration module, examines balance interest banks and purchasing modes in the second-level unit, directly performs targeted purchasing examination on the procurement modes authorized to entrust by the bidding procurement module at the provincial-level demand end, enters the first-level examination module for other purchasing types except the authorized entrust procurement modes to perform balanced interest bank examination of the first-level unit, and finally performs targeted purchasing examination on the upper-level module and the protocol inventory module according to the purchasing modes (see fig. 3).
Specifically, the primary unit examination module comprises a primary demand balance bank examination unit and a primary purchasing mode examination unit. The first-level demand balance interest bank examination unit is used for examining the first-level material purchasing request, carrying out first-level demand balance interest bank examination according to the first-level purchasing information, examining the material reserve quantity in the first-level unit reserve resource pool, determining the actual engineering project required quantity, and forming a new first-level material purchasing request. And then, the primary demand balance interest rate examination unit sends a new primary material purchasing request to a primary purchasing mode examination unit. The first-level purchasing mode examining unit is used for examining the purchasing mode of the first-level purchasing information in the new first-level material purchasing request: when the purchasing mode is single source purchasing or batch purchasing, a new primary material purchasing request is sent to a superior examination module; when the purchasing mode is authorized entrusted purchasing, a new primary material purchasing request is sent to the bid inviting purchasing module; and when the purchasing mode is protocol inventory purchasing, sending a new primary material purchasing request to the protocol inventory examination module. The process basically completes the first-level unit material purchasing request declaration flow chart (see fig. 2).
The first-level unit examination module also comprises a first-level unit demand unit, which is used for detecting whether the purchasing mode in the first-level purchasing information is protocol inventory purchasing or not when the first-level unit examination module receives a first-level material purchasing request, if so, merging the material demand quantity belonging to the protocol inventory purchasing, and if not, not merging; and then sending the combined primary material purchasing request or the uncombined primary material purchasing request to a primary demand balance interest bank examination unit. For example, the same materials in the national network agreement inventory are combined in the required quantity of the materials, and the same materials in the network province agreement inventory are combined in the required quantity of the materials.
Specifically, the secondary unit examination module comprises a secondary demand balance bank examination unit and a secondary purchasing mode examination unit. And the secondary demand balance interest bank examination unit is used for examining the secondary material purchasing request, carrying out secondary demand balance interest bank examination according to secondary purchasing information, examining the material reserve quantity in the secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a new secondary material purchasing request. And then, the secondary demand balance interest rate examination unit sends a new secondary material purchasing request to a secondary purchasing mode examination unit. The second-level purchasing mode examining unit is used for examining the purchasing mode of the second-level purchasing information in the new second-level material purchasing request: when the purchasing mode is single-source purchasing or batch purchasing, a new secondary material purchasing request is sent to the primary examination module, when the purchasing mode is authorized entrusting purchasing, the new secondary material purchasing request is sent to the bid inviting purchasing module, and when the purchasing mode is agreement inventory purchasing, the new secondary material purchasing request is sent to the primary examination module.
When the secondary purchasing mode is single-source purchasing or batch purchasing or agreement inventory purchasing, the primary examination module is required to be entered for examination. Therefore, the primary demand balance interest bank examination unit is also used for examining a new secondary material purchasing request, carrying out primary demand balance interest bank examination on secondary purchasing information of the new secondary material purchasing request, checking the material reserve quantity in a secondary unit reserve resource pool, determining the actual engineering project demand quantity and forming a secondary balance material purchasing request. And then, the primary demand balance profit bank examination unit sends a secondary balance material purchasing request to the primary purchasing mode examination unit. The first-level purchasing mode examining unit is also used for examining whether the purchasing mode of the second-level purchasing information in the second-level balancing material purchasing request is protocol inventory purchasing, if so, sending the second-level balancing material purchasing request to the protocol inventory examining module, and if not, sending the second-level balancing material purchasing request to the higher-level examining module. The process basically completes the flow chart of the declaration of the secondary unit material purchasing request (see fig. 3).
The second-level unit examination module further comprises a second-level unit demand unit, and the second-level unit demand unit is used for detecting whether the purchase mode in the second-level purchase information is protocol inventory purchase or not when a second-level material purchase request is received, merging the material demand quantity belonging to the protocol inventory purchase if the purchase mode in the second-level purchase information is the protocol inventory purchase, and not merging the material demand quantity if the purchase mode in the second-level purchase information is the protocol inventory; and then sending the combined secondary material purchasing request or the uncombined secondary material purchasing request to a secondary demand balance interest bank examination unit. For example, the same materials in the national network agreement inventory are combined in the required quantity of the materials, and the same materials in the network province agreement inventory are combined in the required quantity of the materials.
And the superior examination module is used for examining a new primary material purchasing request and a secondary balance material purchasing request, and generating purchasing data after examining and passing financial budgets. Taking the first-level material purchasing request as an example, the purchasing information in the first-level material purchasing request is examined and approved, and the financial examination and approval, the item WBS information examination and the approximate calculation examination are sequentially carried out on the purchasing quantity and the purchasing price. And checking the national network reference price list in the checking process, checking whether the national network reference price list accords with the current annual budget/current month/current season budget, forming specific purchasing data after the checking is passed, and sending the specific purchasing data to a third-party supplier for purchasing. Likewise, secondary balance material procurement requests are reviewed as well.
And the agreement inventory examination module is used for examining a new primary material purchasing request and a new secondary balance material purchasing request and generating purchasing data after the examination is passed. The agreement stock comprises a plurality of types, each agreement stock already determines a corresponding supplier when an agreement is signed, and for this purpose, by determining the agreement stock type of the material required to be purchased, purchasing data of the corresponding supplier is formed and sent to the supplier.
And the bid inviting and purchasing module is used for examining the new primary material purchasing request and the new secondary material purchasing request and generating purchasing data after the examination is passed. The bid inviting purchasing module specifically comprises a material purchasing demand unit and a bid inviting purchasing unit. The material purchasing demand unit is used for classifying the purchasing materials of the first-level material purchasing request or the new second-level material purchasing request and performing different bid purchasing according to the material types. Wherein, the materials which are purchased in a matching way need to be purchased in a unified way. And after the classification of the material purchasing demand unit is finished, sending the material purchasing demand unit to a bid purchasing unit to perform bid purchasing according to the material category. The tender purchasing module further comprises a supplier unit, and the supplier unit stores a supplier list and materials corresponding to the material categories. And the tender purchasing unit tenders the corresponding materials to the related suppliers according to the storage information of the supplier unit to form purchasing data of the corresponding suppliers and sends the purchasing data to the suppliers.
The system also comprises a first-level unit reserve plan examination module which is used for examining the first-level unit reserve plan sent by the market-level demand end and sending examination qualified information to the market-level demand end after the examination is passed. The city-level demand end sends a first-level material purchasing request to a first-level unit declaration module based on a first-level unit reserve plan. The primary unit reserve plan comprises a project material inventory and a technical specification corresponding to the primary unit project. The engineering material inventory comprises material codes, technical specification IDs and required quantity. And the city level design unit designs the project entrusted by the project unit to complete the project material inventory, and the project unit audits the project material inventory. After the audit is passed, the data are reported to the market-level material department to form a first-level unit reserve plan.
Specifically, the primary unit reserve plan examination module comprises a rule examination library and a primary unit examination unit. The rule examination library is used for storing information integrity rules, purchasing information specification rules and technical specification rules. The information integrity rule mainly indicates whether a level unit reserve plan is complete or not and whether engineering project information and purchasing information are complete or not. The information integrity rule is set based on the information contained in the unit-of-class reserve plan. The purchasing information standard rule is mainly determined according to a purchasing catalogue, and whether purchasing information is set according to the purchasing catalogue is determined. The technical specification rule is a technical rule set according to national standards, and the design meeting the regulations is required to be carried out on projects with different voltage levels. The first-level unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the first-level unit for information integrity, purchasing information standardization and technical compliance, if the examination is passed, sending examination qualified information to the market-level demand end, and if the examination is not passed, sending examination unqualified information to the market-level demand end. The information integrity rule comprises whether the information in the primary unit reserve plan is missing, if the Null exists, the primary unit examination unit feeds back the abnormal examination information, and the information integrity rule also comprises the condition that the information in the primary unit reserve plan is filled in by mistake (determined according to the filling range standard). For example, if the procurement information lacks national standard materials, the primary unit review unit feeds back material normative abnormal information. For example, if the filling range of the project voltage class is 500 kV, 220kV, 110kV, 35 kV, and the actually declared voltage class is 111 kV, the first-level unit review unit feeds back information to fill the normative abnormality information. The purchasing information specification rules comprise rules whether the material subclass, the medium class and the large class are in the purchasing catalogue. The purchasing catalog is formed by the corresponding relation table of purchasing category and material classification, and is indexed by material code. The first-level unit examination unit also examines the technical compliance of the monthly reservation plan according to the technical standard rules prestored in the power grid material examination system. For example, for the requirement of the subclass of capacitor bank series reactor', the material description contains hollow, the number of the hollow is 3 times of the required number of the subclass of frame-type capacitor bank or integrated capacitor bank under the same engineering, the material description contains iron cores, and the number of the hollow is consistent with the required number of the subclass of frame-type capacitor bank or integrated capacitor bank under the same engineering. For another example, the subclass is "grounding transformer", the material description includes "10 KV", the requirement corresponds to the requirement of the subclass of the engineering name including "arc suppression coil", and the two requirements should be the same solidification ID. Also for example, the subclass is "capacitor bank series reactors", which cannot be purchased separately. The requirements under the engineering name should include a subclass of "collective capacitor bank (without reactor)" or "frame capacitor (without reactor)", and the two requirements should be the same curing ID. Such as the above example, the technical specification rules are set according to the national standard, and the technical specification rules are set according to different national standards according to the design project specification and grade.
The system also comprises a secondary unit reserve plan examination module which is used for examining the secondary unit reserve plan sent by the county level demand end and sending examination qualified information to the county level demand end after the examination is passed. And the county-level demand end sends a secondary material purchasing request to the secondary unit declaration module based on the secondary unit reserve plan. The secondary unit reserve plan comprises a project material inventory and a technical specification corresponding to the secondary unit project. The engineering material inventory comprises material codes, technical specification IDs and required quantity. And the county level design unit designs the project entrusted by the project unit to complete the project material inventory, and the project unit audits the project material inventory. And after the audit is passed, reporting the data to a county level material department to form a secondary unit reserve plan.
Specifically, the secondary unit reserve plan examination module comprises a rule examination library and a secondary unit examination unit. The rule examination library is used for storing information integrity rules, purchasing information specification rules and technical specification rules. The content stored in the rule checking library is basically similar to that of the rule checking library of the first-level unit reserve plan checking module, the only difference is that the grades of the accessed projects are different according to the county-level and city-level qualities, and the rule standard is determined according to the project grades. That is, the rule checking library of the secondary unit reserve plan checking module does not store the high standard rule of the project which can be accepted by the primary unit. The rule checking library of the first-level unit reserve plan checking module can store the rule that the first-level unit and the second-level unit can both receive the project, or only store the high-standard rule that the first-level unit can receive the project. And the secondary unit examination unit is used for calling examination rules in the rule examination library, examining the monthly storage plan of the secondary unit for information integrity, purchasing information standardization and technical compliance, if the examination is passed, sending examination qualified information to the county level demand end, and if the examination is not passed, sending examination unqualified information to the county level demand end. The information integrity rule comprises whether the information in the secondary unit reserve plan is missing, if the Null exists, the secondary unit examination unit feeds back the abnormal examination information, and the information integrity rule also comprises the condition that the information in the secondary unit reserve plan is filled in by mistake (determined according to the filling range standard). For example, if the procurement information lacks national standard materials, the second-level unit review unit feeds back the material normative abnormal information. For example, if the filling range of the project voltage class is 500 kV, 220kV, 110kV, 35 kV, and the actually declared voltage class is 111 kV, the second-level unit review unit feeds back information to fill the normative abnormality information. The purchasing information specification rules comprise rules whether the material subclass, the medium class and the large class are in the purchasing catalogue. The purchasing catalog is formed by the corresponding relation table of purchasing category and material classification, and is indexed by material code. And the secondary unit examination unit also examines the technical compliance of the monthly reservation plan according to a technical specification rule prestored in the power grid material examination system. For example, for the requirement of the subclass of capacitor bank series reactor', the material description contains hollow, the number of the hollow is 3 times of the required number of the subclass of frame-type capacitor bank or integrated capacitor bank under the same engineering, the material description contains iron cores, and the number of the hollow is consistent with the required number of the subclass of frame-type capacitor bank or integrated capacitor bank under the same engineering. For another example, the subclass is "grounding transformer", the material description includes "10 KV", the requirement corresponds to the requirement of the subclass of the engineering name including "arc suppression coil", and the two requirements should be the same solidification ID. Also for example, the subclass is "capacitor bank series reactors", which cannot be purchased separately. The requirements under the engineering name should include a subclass of "collective capacitor bank (without reactor)" or "frame capacitor (without reactor)", and the two requirements should be the same curing ID. Such as the above example, the technical specification rules are set according to the national standard, and the technical specification rules are set according to different national standards according to the design project specification and grade.
It will be appreciated by persons skilled in the art that the embodiments of the invention described above and shown in the drawings are given by way of example only and are not limiting of the invention. The objects of the present invention have been fully and effectively accomplished. The functional and structural principles of the present invention have been shown and described in the examples, and any variations or modifications of the embodiments of the present invention may be made without departing from the principles.