Intelligent management system and method for energy group informatization whole process

文档序号:9005 发布日期:2021-09-17 浏览:39次 中文

1. An energy group informatization whole-process intelligent management system is characterized by comprising an energy group informatization project management system (6), wherein the energy group informatization project management system (6) comprises an informatization project establishment management module (1), an informatization project start-up management module (2), an informatization project development management module (3), an informatization project on-line management module (4) and an informatization project acceptance management module (5);

the informationized project establishment management module (1) comprises a project establishment application module (7), a project establishment application module (8), a project category analysis module (9), an organization establishment application examination module (10), a project establishment examination and approval module (11), a project classification module (12), an establishment application confirmation module (13), a project establishment application summarizing module (14), a project establishment examination and approval total module (15) and a project issuing module (16), wherein the project establishment application module (7), the project category analysis module (9) and the project establishment examination and approval module (11) are sequentially connected, and the project establishment application module (8), the organization establishment application examination and approval module (10), the project classification module (12), the establishment application confirmation module (13), the project establishment application module summarizing (14), the project establishment examination and approval total module (15), The project issuing module (16) is sequentially connected, the project category analysis module (9) is connected with the organization project establishment application auditing module (10), the project establishment approval module (11) and the project classification module (12) are both connected with the project establishment application summarizing module (14), and the project issuing module (16) is connected to the project work starting application module (17);

the information project start-up management module (2) comprises a project start-up application module (17), a major project analysis module (18), a first approved project start-up application module (19), an organization project start-up review module (20), a small-amount project analysis module (21), a second approved project start-up application module (22), a participation project start-up review module (23) and a third approved project start-up application module (24), wherein the project start-up application module (17), the major project analysis module (18) and the first approved project start-up application module (19) are sequentially connected, the organization project start-up review module (20), the small-amount project analysis module (21) and the second approved project start-up application module (22) are sequentially connected, and the major project analysis module (18) and the second approved project start-up review module (23) are both connected with the organization project start-up review module (20), the organization project start-up auditing module (20) and the small-amount project analyzing module (21) are connected with a first approved project start-up application module (24), and the first approved project start-up application module (19), the second approved project start-up application module (22) and the third approved project start-up application module (24) are connected to a system development module (25);

the information project development management module (3) comprises a system development module (25) and a system debugging module (26), wherein the system development module (25) is connected with the system debugging module (26);

the information project online management module (4) comprises a project online application module (27), an organization online review conference module (28), a participation online review module (29) and a review result analysis module (30), wherein the project online application module (27) and the participation online review module (29) are connected with the organization online review conference module (28), the organization online review conference module (28) is connected with the review result analysis module (30), the review result analysis module (30) is connected with the project online application module (27), and the review result analysis module (30) is connected with the project trial operation module (31);

the informationized project acceptance management module (5) comprises a project trial operation module (31), an acceptance application module (32), an organization project acceptance review conference module (33), a participation project acceptance review conference module (34), an acceptance result analysis module (35) and a formal operation module (36), wherein the project trial operation module (31), the acceptance application module (32), the organization project acceptance review conference module (33), the acceptance result analysis module (35) and the formal operation module (36) are sequentially connected, the participation project acceptance review conference module (34) is connected with the organization project acceptance review conference module (33), and the acceptance result analysis module (35) is connected with the acceptance application module (32).

2. The working method of the energy group informatization whole-process intelligent management system according to claim 1, characterized by comprising the following steps:

A. the whole process of the informationized project is managed on line; the method comprises the steps that a data interconnection and intercommunication mechanism is established through an information project establishment management module (1), an information project start-up management module (2), an information project development management module (3), an information project on-line management module (4) and an information project acceptance management module (5) in an energy group information project management system (6), the state is tracked in real time, each link and time of a project are analyzed, and the whole process on-line management of the information project is realized;

B. performing full logic handling on the informationized project; each handling link of the information project establishment management module (1), the information project start-up management module (2), the information project development management module (3), the information project online management module (4) and the information project acceptance management module (5) is correlated with each other, so that ordered management of the information projects is realized, and the construction quality and efficiency of the information projects are improved;

C. setting up items for an information project; in the information project establishment management module (1), after project establishment application and project type analysis, if the project is a system establishment project, the project establishment examination and verification are organized, and if the project is a self-establishment project, the project establishment examination and approval are organized by an application unit; the secondary unit needs to apply for an information project, organization project establishment application auditing is carried out after project establishment application, after project classification is judged, if the project is a unified project, project establishment application confirmation is carried out, if the project is not the unified project, project establishment application summarization is carried out, and then project establishment is realized through a project establishment approval total module (15) and a project issuing module (16);

D. information project operation management; in the information project start-up management module (2), after a project is issued, a project start-up application and a major project analysis are carried out, if the project is a non-major project, the project start-up application is approved, and then a project development stage is carried out; if the project is a major project, the project is organized by a second level unit to be approved, and the project approval application is approved by the informatization subject meeting; if the project is a small-amount project, the information department of the second level unit approves the application of the start worker;

F. information project development online management; in the information project development management module (3), after the information project is started, the system development stage is started, then the system debugging stage is started, and real-time monitoring and tracking are realized;

G. online management of the information project; in the information project online management module (4), the system enters an online stage after debugging is finished, whether an online condition is met is determined through project online application and an online review conference, an applicant is required to participate in online review, an acceptance link is entered through review, and if the online condition is not met, the project online application is returned;

H. checking and accepting the informatization project; in the information project acceptance management module (5), after the information project finishes on-line evaluation, the information project enters a project trial operation stage, a project acceptance evaluation meeting is applied and organized through acceptance, an applicant participates in the project acceptance evaluation, whether the acceptance requirement is met is determined through the acceptance evaluation, the information project enters a formal operation stage, and if the acceptance requirement is not met, the information project is returned to reapplication for acceptance.

Background

The new generation information technology represented by the internet is a scientific and technological innovation field with the most concentrated global research and development investment, the most active innovation, the most extensive application and the strongest radiation driving effect, the emerging technologies such as mobile internet, big data, cloud computing, internet of things, artificial intelligence, block chain and the like are accelerated to be infiltrated and fused into various fields, the production and living modes of people are deeply changed, the network connection is from the interconnection of people to the interconnection of everything, and the technical application is shifted from the consumption-oriented link to the production-oriented link. With the rapid remodeling of global energy management patterns, a new round of information technology revolution develops rapidly, the global acceleration is promoted to enter the digital economic era, China insists on using structural reformation of a supply side as a main line to promote energy structure adjustment and industrial structure optimization and upgrading, and the energy production and consumption modes are undergoing great transformation. The energy group enterprises actively deploy informatization construction, and the information project development and construction are mainly carried out in the fields of production management, business management, scientific and technological management, human resource management, financial management, office integration and the like, so that the modernization of the enterprise industry is boosted by the informatization construction, and the integration of informatization resources supports the group management and control system construction and the guarantee strategy development.

At present, energy group information construction and management have a lot of difficulties and problems, and mainly comprise: (1) the energy group information project construction does not form a management method and a management mechanism for efficient coordination. (2) The information project construction management covers a wide project range, multiple types, multiple requirements, difficult management cooperation, low efficiency and long period. (3) The link full-period management of information project establishment, work starting, construction, online, acceptance inspection and the like is not realized. (4) A unified information project full life cycle management system is not established.

Disclosure of Invention

The invention aims to solve the problems that the existing energy group information project construction does not form an efficient coordinated management method and mechanism, the information project construction management is difficult to coordinate, low in efficiency and long in period, the whole-period management of links such as information project establishment, work starting, construction, online and acceptance inspection is not realized, a unified information project whole-life-cycle management system is not established, and the like.

The technical scheme adopted by the invention for solving the problems is as follows: the energy group informatization whole-process intelligent management system is characterized by comprising an energy group informatization project management system, wherein the energy group informatization project management system comprises an informatization project establishment management module, an informatization project start-up management module, an informatization project development management module, an informatization project on-line management module and an informatization project acceptance management module.

The informationized project establishment management module comprises a project establishment application module, a project category analysis module, an organization establishment application examination and verification module, a project establishment examination and approval module, a project classification module, an establishment application confirmation module, a project establishment application summarization module, a project establishment examination and approval total module and a project assignment module, wherein the project establishment application module, the project category analysis module and the project establishment examination and approval module are sequentially connected, the project establishment application module, the organization establishment application examination and approval module, the project classification module, the establishment application confirmation module, the project establishment application summarization module, the project establishment examination and approval total module and the project assignment module are sequentially connected, the project category analysis module is connected with the organization establishment application examination and verification module, and the project establishment examination and approval module and the project classification module are both connected with the project establishment application summarization module, the project issuing module is connected to the project start application module;

the information project start-up management module comprises a project start-up application module, a major project analysis module, a approval project start-up application module I, an organization project start-up examination module, a small-amount project analysis module, an approval project start-up application module II, a participation project start-up examination module and an approval project start-up application module III, wherein the project start-up application module, the major project analysis module and the approval project start-up application module I are sequentially connected, the organization project start-up examination module, the small-amount project analysis module and the approval project start-up application module II are sequentially connected, the major project analysis module and the participation project start-up examination module are connected with the organization project start-up examination module, the organization project start-up examination module and the small-amount project analysis module are connected with the approval project start-up application module III, the approval project start-up application module I, the small-amount project analysis module II and the approval application module III are connected with the approval project start-up application module III, The second approval project start-up application module and the third approval project start-up application module are both connected to the system development module;

the information project development management module comprises a system development module and a system debugging module, and the system development module is connected with the system debugging module;

the information project online management module comprises a project online application module, an organization online review conference module, a participation online review module and a review result analysis module, wherein the project online application module and the participation online review module are connected with the organization online review conference module, the organization online review conference module is connected with the review result analysis module, the review result analysis module is connected with the project online application module, and the review result analysis module is connected to the project trial operation module;

the informationized project acceptance management module comprises a project trial operation module, an acceptance application module, an organization project acceptance review conference module, a participation project acceptance review conference module, an acceptance result analysis module and a formal operation module, wherein the project trial operation module, the acceptance application module, the organization project acceptance review conference module, the acceptance result analysis module and the formal operation module are sequentially connected, the participation project acceptance review conference module is connected with the organization project acceptance review conference module, and the acceptance result analysis module is connected with the acceptance application module.

The energy group informatization whole-process intelligent management system can realize that:

A. and managing the whole process of the information project on line. A data interconnection and intercommunication mechanism is established through an information project establishment management module, an information project start-up management module, an information project development management module, an information project online management module and an information project acceptance management module in the energy group information project management system, the state is tracked in real time, each link and time of a project are analyzed, and the whole process online management of the information project is realized.

B. And (4) performing full logic transaction on the information item. Each handling link of the information project establishment management module, the information project start-up management module, the information project development management module, the information project on-line management module and the information project acceptance management module is correlated, ordered management of the information projects is achieved, and the information project construction quality and efficiency are improved.

C. And (4) setting up management of information projects. In the information project establishment management module, after project establishment application and project type analysis, if the project is a system project, the project establishment examination and verification are organized, and if the project is a self-establishment project, the project establishment examination and approval are organized by an application unit. And the secondary unit needs to apply for an information project, organizes and approves the project establishment application after the project establishment application, judges the project classification, confirms the project establishment application if the project is a unified establishment project, enters the project establishment application summary if the project is not the unified establishment project, and then realizes the project establishment through a project establishment approval total module and a project issuing module.

D. And (5) information project operation management. In the information project start-up management module, after a project is issued, a project start-up application and a major project analysis are carried out, if the project is a non-major project, a project start-up application is examined, and then a project development stage is carried out; if the project is a major project, the project is organized by a second level unit to be approved, and the project approval application is approved by the informatization subject meeting; if the project is a small-amount project, the information department of the second level unit approves the application of the start work.

F. And (4) online management of information project development. In the information project development management module, after the information project is started, the system development stage is started, then the system debugging stage is started, and real-time monitoring and tracking are achieved.

G. And (5) online management of the information project. In the information project online management module, the system enters an online stage after debugging is completed, whether online conditions are met is determined through project online application and an online review meeting organization, an applicant is required to participate in online review, a checking link is entered through review, and if the online conditions are not met, the project online application is returned.

H. And (5) checking and managing the information project. In the information project acceptance management module, after the information project finishes on-line evaluation, the information project enters a project trial operation stage, applies and organizes a project acceptance evaluation conference through acceptance, and an applicant participates in the project acceptance evaluation and determines whether the acceptance requirements are met through the acceptance evaluation and enters a formal operation stage, and if the acceptance requirements are not met, the information project returns to reapply for acceptance.

Compared with the prior art, the invention has the following advantages and effects: (1) a full-process informatization project management mode and a process method are established, the full-process online management is realized by adopting an informatization technical mode, and the construction efficiency of the informatization project is improved. (2) A brand-new and comprehensive management method is established, the informatization project is divided into links of informatization project establishment management, startup management, development management, online management and acceptance management, and dynamic management and tracking are realized. (3) The online real-time tracking and online management of the information management process are realized through the information project management system. (4) An information project establishment management module is established, and online process management and tracking of project establishment, project classification, establishment examination and verification, examination and approval, issuing and the like are achieved. (5) An information project start-up management module is established, and on-line process management and tracking of project start-up application, major projects, start-up audit, start-up approval and the like are achieved. (6) An information project development management module is established, and online process management and tracking of system development and system debugging are achieved. (7) An information project online management module is established, and online process management and tracking such as online application, online review, project review and the like are realized. (8) An information project acceptance management module is established, and online process management and tracking of project trial operation, acceptance application, acceptance review, formal operation and the like are realized.

Drawings

FIG. 1 is a schematic diagram of the system architecture of the present invention.

In the figure: an information project establishment management module 1, an information project start-up management module 2, an information project development management module 3, an information project on-line management module 4, an information project acceptance management module 5, an energy group information project management system 6, a project establishment application module 7, a project establishment application module 8, a project category analysis module 9, an organization establishment application review module 10, a project establishment approval examination module 11, a project classification module 12, an establishment application confirmation module 13, a project establishment application summary module 14, a project establishment examination and approval total module 15, a project assignment module 16, a project start-up application module 17, a major project analysis module 18, a first approved project start-up application module 19, a project start-up examination module 20, a small-amount project analysis module 21, a second approved project start-up application module 22, a project start-up examination participation module 23, a project start-up examination module, A third approved project initiating application module 24, a system development module 25, a system debugging module 26, a third project online application module 27, an organization online review conference module 28, a participating online review module 29, a review result analysis module 30, a third project trial operation module 31, a third acceptance application module 32, a third organization project acceptance review conference module 33, a third participating project acceptance review module 34, a third acceptance result analysis module 35 and a third formal operation module 36.

Detailed Description

The present invention will be described in further detail below by way of examples with reference to the accompanying drawings, which are illustrative of the present invention and are not to be construed as limiting the present invention.

Examples

Referring to fig. 1, in this embodiment, an energy group informatization whole-process intelligent management system includes an energy group informatization project management system 6, and the energy group informatization project management system 6 includes an informatization project establishment management module 1, an informatization project start-up management module 2, an informatization project development management module 3, an informatization project online management module 4, and an informatization project acceptance management module 5.

The information project establishment management module 1 comprises a project establishment application module 7, an establishment project establishment application module 8, a project category analysis module 9, an organization establishment application auditing module 10, a project establishment approval module 11, a project classification module 12, an establishment application confirmation module 13, a project establishment application summarizing module 14, a project establishment approval summarizing module 15 and a project issuing module 16, wherein the project establishment application module 7, the project category analysis module 9 and the project establishment approval module 11 are sequentially connected, the establishment project establishment application module 8, the organization establishment application auditing module 10, the project classification module 12, the establishment application confirmation module 13, the project establishment application summarizing module 14, the project establishment approval reviewing module 15 and the project issuing module 16 are sequentially connected, the project category analysis module 9 is connected with the organization establishment application auditing module 10, the project establishment approval reviewing module 11 and the project classification module 12 are both connected with the project establishment application summarizing module 14, the project issuing module 16 is connected to the project start application module 17;

the information project start-up management module 2 comprises a project start-up application module 17, a major project analysis module 18, a first approved project start-up application module 19, an organization project start-up examination module 20, a small-amount project analysis module 21, a second approved project start-up application module 22, a second participated project start-up examination module 23 and a third approved project start-up application module 24, wherein the project start-up application module 17, the major project analysis module 18 and the first approved project start-up application module 19 are sequentially connected, the organization project start-up examination module 20, the small-amount project analysis module 21 and the second approved project start-up application module 22 are sequentially connected, the major project analysis module 18 and the second participated project start-up examination module 23 are both connected with the organization project start-up examination module 20, the organization project start-up examination module 20 and the small-amount project analysis module 21 are both connected with the third approved project start-up application module 24, the first approved item start-up application module 19, the second approved item start-up application module 22 and the third approved item start-up application module 24 are all connected to the system development module 25;

the information project development management module 3 comprises a system development module 25 and a system debugging module 26, wherein the system development module 25 is connected with the system debugging module 26;

the information project online management module 4 comprises a project online application module 27, an organization online review conference module 28, an online review participation module 29 and a review result analysis module 30, wherein the project online application module 27 and the online review participation module 29 are connected with the organization online review conference module 28, the online review organization conference module 28 is connected with the review result analysis module 30, the review result analysis module 30 is connected with the project online application module 27, and the review result analysis module 30 is connected with a project trial operation module 31;

the information project acceptance management module 5 comprises a project trial operation module 31, an acceptance application module 32, an organization project acceptance review conference module 33, a participation project acceptance review module 34, an acceptance result analysis module 35 and a formal operation module 36, wherein the project trial operation module 31, the acceptance application module 32, the organization project acceptance review conference module 33, the acceptance result analysis module 35 and the formal operation module 36 are sequentially connected, the participation project acceptance review module 34 is connected with the organization project acceptance review conference module 33, and the acceptance result analysis module 35 is connected with the acceptance application module 32.

The working method comprises the following steps:

A. and managing the whole process of the information project on line. A data interconnection and intercommunication mechanism is established through an information project establishment management module 1, an information project start-up management module 2, an information project development management module 3, an information project online management module 4 and an information project acceptance management module 5 in an energy group information project management system 6, the state is tracked in real time, each link and time of a project are analyzed, and the whole process online management of the information project is realized.

B. And (4) performing full logic transaction on the information item. Each handling link of the information project establishment management module 1, the information project start-up management module 2, the information project development management module 3, the information project online management module 4 and the information project acceptance management module 5 is correlated with each other, so that ordered management of the information projects is realized, and the construction quality and efficiency of the information projects are improved.

C. And (4) setting up management of information projects. In the information project establishment management module 1, after project establishment application and project type analysis, if the project is a system establishment project, the project establishment examination and verification are organized, and if the project is a self-establishment project, the project establishment examination and approval are organized by an application unit. The secondary unit needs to apply for information projects, organization project establishment application auditing is carried out after project establishment application, after project classification is judged, project establishment application confirmation is carried out if the project is a unified project, project establishment application summarization is carried out if the project is not a unified project, and project establishment is realized through a project establishment approval total module 15 and a project issuing module 16.

D. And (5) information project operation management. In the information project start-up management module 2, after a project is issued, a project start-up application and a major project analysis are carried out, if the project is a non-major project, a project start-up application is examined, and then a project development stage is carried out; if the project is a major project, the project is organized by a second level unit to be approved, and the project approval application is approved by the informatization subject meeting; if the project is a small-amount project, the information department of the second level unit approves the application of the start work.

F. And (4) online management of information project development. In the information project development management module 3, after the information project is started, the system development stage is entered, then the system debugging stage is entered, and real-time monitoring and tracking are realized.

G. And (5) online management of the information project. In the information project online management module 4, the system enters an online stage after debugging is completed, whether online conditions are met is determined through project online application and an online review conference organization, an applicant is required to participate in online review, a checking link is entered through review, and if not, project online application is returned.

H. And (5) checking and managing the information project. In the informatization project acceptance management module 5, after the informatization project finishes on-line evaluation, the project enters a project trial operation stage, applies and organizes a project acceptance evaluation meeting through acceptance, and an applicant participates in the project acceptance evaluation at the same time, decides whether the acceptance requirement is met through the acceptance evaluation, enters a formal operation stage, and returns to reapply the acceptance if the acceptance requirement is not met.

Those not described in detail in this specification are well within the skill of the art.

Although the present invention has been described with reference to the above embodiments, it should be understood that the scope of the present invention is not limited thereto, and that various changes and modifications can be made by those skilled in the art without departing from the spirit and scope of the present invention.