1. The utility model provides a scaffold frame is wall subassembly even, includes the steel sheet, and in this steel sheet one end pre-buried income concrete wall body, the adapted scaffold frame, its characterized in that are connected directly or indirectly to the steel sheet other end: it still includes steel pipe and wedge picture peg, and it has vertical slot to open on this steel pipe, and the vertical bisector of this vertical slot coincides with the axial lead of steel pipe, and this vertical slot is close to steel pipe one end, the part that exposes of steel sheet has also opened a vertical slot, the steel sheet lower surface is taken on the steel pipe, just vertical slot local on vertical slot on the steel sheet and the steel pipe is relative, and vertical slot and vertical slot coincide at the projection part of same horizontal plane, wedge picture peg lower extreme is narrow, the upper end is wide, wedge picture peg top-down inserts in relative vertical slot and the vertical slot, steel sheet and steel pipe are extruded respectively to wedge picture peg both sides, make adjacent steel pipe tip support on the adapted concrete wall, and the adapted scaffold is fixed on the steel pipe.

2. A scaffolding wall assembly as claimed in claim 1, wherein: and aluminum foil waterproof adhesive tapes are wound on the wedge-shaped inserting plate and the steel plates and the steel pipes at the periphery of the wedge-shaped inserting plate so as to fix the wedge-shaped inserting plate.

3. A scaffolding wall assembly as claimed in claim 1, wherein: the steel pipe clamp also comprises one or more clamps which clamp the steel plates and the steel pipes which are in mutual contact.

4. A scaffolding-wall assembly as claimed in claim 1, 2 or 3, in which: the cross section of the exposed part of the steel plate is arc-shaped, and the lower surface of the steel plate is matched with the outer wall of the steel pipe.

Background

The utility model discloses a novel wall connecting piece device which is arranged between a wall body and a scaffold and has the publication number of CN 204571267U, and is disclosed in the utility model Chinese utility model patent which is published in 19/08/2015, and comprises a wall attaching bottom plate, a fixing bolt, a connecting pipe and a horizontal rotatable adjusting component, wherein through holes are formed at four corners of the wall attaching bottom plate, and the fixing bolt penetrates through the through holes to anchor the wall attaching bottom plate on the wall body; the horizontal rotatable adjusting assembly consists of a pin joint part and a connecting part, the pin joint part comprises a horizontal clamping plate and an inserting plate inserted into the clamping plate, and a vertical pin shaft penetrates through the overlapped part of the clamping plate and the inserting plate to enable the inserting plate to be horizontally rotatable and adjusted in the clamping plate; the one end welding between two parties of pin junction portion is on pasting the wall bottom plate, and the other end welds on connecting portion between two parties, connecting portion are vertical connecting plate, and this connecting plate welds with the one end of connecting pipe, and the other end and the scaffold frame of connecting pipe pass through the fastener and are connected.

The utility model discloses a chinese utility model patent that 11 of 2019, 19 of month, publication number is CN 209653366U discloses a building construction is band iron formula rigidity wall spare even for scaffold, should link the wall spare with the screw thread post fixed, the use screw thread atress is out of shape easily, the dismouting is inconvenient, does not have the function of taut scaffold.

Disclosure of Invention

The invention aims to solve the technical problem of how to overcome the defects in the prior art and provide a scaffold wall connecting assembly which is convenient to disassemble and assemble and convenient to erect.

For solving above-mentioned technical problem, this scaffold frame is wall subassembly even includes the steel sheet, and in this steel sheet one end was pre-buried to go into the concrete wall, the steel sheet other end was direct or indirect connects adapted scaffold frame, its characterized in that: it still includes steel pipe and wedge picture peg, and it has vertical slot to open on this steel pipe, and the vertical bisection face of this vertical slot coincides with the axial lead of steel pipe, and this vertical slot is close to steel pipe one end, the part that exposes of steel sheet has also opened a vertical slot, the steel sheet lower surface is taken on the steel pipe, just vertical slot part on the vertical slot on the steel sheet is relative with the vertical slot on the steel pipe, and vertical slot and vertical slot coincide at the projection part of same horizontal plane, wedge picture peg lower extreme is narrow, the upper end is wide, wedge picture peg top-down inserts in relative vertical slot and the vertical slot, steel sheet and steel pipe are extruded respectively to wedge picture peg both sides, make adjacent steel pipe tip support on the adapted concrete wall, and the adapted scaffold is fixed on the steel pipe. The lower end of the wedge-shaped inserting plate is exposed out of the vertical slot.

By the design, one end of the steel pipe close to the wall automatically props against the concrete wall body to prevent the matched scaffold from inclining inwards, the steel plate and the steel pipe are connected into a whole by the wedge-shaped inserting plate to prevent the frame body from inclining outwards, so that an internal support is formed and pulled outwards, and the integral stability of the matched scaffold is guaranteed; the steel sheet can effectively avoid keeping somewhere the construction hole when the secondary structure is under construction, effectively reduces outer wall seepage risk.

When the matched scaffold and the steel pipe need to be dismantled, the wedge-shaped inserting plate can be taken down only by knocking the lower end of the wedge-shaped inserting plate from bottom to top by using a hammer, and then the steel pipe is dismantled and reused. And finally, cutting off the exposed steel plate on the concrete wall by using gas cutting or an electric grinding wheel, which is very convenient.

Preferably, aluminum foil waterproof adhesive tapes are wound on the wedge-shaped plugboard and the steel plates and the steel pipes around the wedge-shaped plugboard so as to fix the wedge-shaped plugboard. The aluminum foil waterproof adhesive tape can be selected from the power cable aluminum foil waterproof adhesive tape disclosed in the Chinese utility model patent with the publication number of CN 207731700U. By the design, the wedge-shaped inserting plate can be prevented from being separated from the wedge-shaped inserting plate due to vibration or impact of external force.

Preferably, the steel pipe clamp further comprises one or more clamps which clamp the steel plates and the steel pipes which are in contact with each other. The clamp can be selected from a clamp component disclosed in the Chinese utility model with the publication number of CN 203856816U or a hanging-pulling type clamp shell clamp disclosed in the Chinese utility model with the publication number of CN 204284724U. So design, steel sheet and steel pipe are hooped together, and are more firm.

Preferably, the cross section of the exposed part of the steel plate is arc-shaped, and the lower surface of the steel plate is matched with the outer wall of the steel pipe. By the design, the contact area between the two is large, and the two are firmer.

The scaffold wall-connecting component has the advantages of simple structure, convenience in disassembly and assembly, internal support and external pull, and automatic fastening, and is suitable for fixing external wall scaffolds of various buildings.

Drawings

The scaffold wall connecting assembly of the invention is further described with reference to the accompanying drawings:

fig. 1 is a schematic perspective view of a first embodiment of the scaffolding wall-connecting assembly;

fig. 2 is a schematic perspective exploded view of a first embodiment of the scaffold wall connecting assembly.

In the figure: 1 is a steel plate, 2 is a concrete wall, 3 is a steel pipe, 4 is a wedge-shaped inserting plate, 5 is a vertical slot, and 6 is a vertical longitudinal slot.

Detailed Description

The first implementation mode comprises the following steps: as shown in fig. 1-2, the scaffold wall-connecting assembly comprises a steel plate 1, one end of the steel plate 1 is embedded into a concrete wall 2, and the other end of the steel plate 1 is directly or indirectly connected with a matched scaffold (not shown in the figure), and is characterized in that: the steel pipe is characterized by further comprising a steel pipe 3 and a wedge-shaped inserting plate 4, wherein a vertical slot 5 is formed in the steel pipe 3, the vertical plane of the vertical slot 5 coincides with the axial lead of the steel pipe 3, the vertical slot 5 is close to one end of the steel pipe 3, a vertical longitudinal slot 6 is also formed in the exposed part of the steel plate 1, the lower surface of the exposed part 1 of the steel plate is lapped on the steel pipe 3, the vertical longitudinal slot 6 in the steel plate 1 is locally opposite to the vertical slot 5 in the steel pipe 3, the vertical longitudinal slot 6 and the vertical slot 5 coincide in the same horizontal plane, the lower end of the wedge-shaped inserting plate 4 is narrow, the upper end of the wedge-shaped inserting plate 4 is wide, the wedge-shaped inserting plate 4 is inserted into the vertical longitudinal slot 6 and the vertical slot 5 from top to bottom, the steel plate 1 and the steel pipe 3 are respectively extruded at two sides of the wedge-shaped inserting plate 4 (exactly, the side wall of the end part of the adjacent vertical slot 6 and the side wall of the vertical slot 5 are respectively extruded at the two sides), the end of the corresponding steel pipe 3 is abutted against the concrete wall 2, and the scaffold is fixed on the steel pipe 3. The cross section of the exposed part of the steel plate 1 is arc-shaped, and the lower surface of the steel plate is matched with the outer wall of the steel pipe 3.

The second embodiment: the wedge-shaped inserting plate 4 and the steel plate 1 and the steel pipe 3 around the wedge-shaped inserting plate are wound with aluminum foil waterproof adhesive tapes so as to fix the wedge-shaped inserting plate 4 and prevent the wedge-shaped inserting plate from falling off, and the rest structures are as described in the first embodiment and are not shown in the figure.

The third embodiment is as follows: the steel plate and steel pipe clamp further comprises one or more clamping bands, wherein the clamping bands clamp the steel plate 1 and the steel pipe 3 which are in contact with each other, and the rest structures are as described in the first embodiment or the second embodiment and are not shown in the drawing.