Construction method of novel fast-assembly permanent dam
1. A novel fast-assembly permanent dam construction method is disclosed, wherein figure 1 is a front view of a dam wall of the slope protection dam, and comprises a flood protection building module (1), a water suction port (2), a water outlet (3), a module splicing part (4), a rubber outer surface layer (5), a water facing surface (6), a vacuum connecting groove (7) and the like; fig. 2 is a sectional view of a single flood protection building module, comprising a movable top panel (7), a fixed drill bit means (8), a water line (9), a pressure detection line (10), a tee connection (11), a water pump (12), a valve (13), a vacuum suction pump (14), etc.
2. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: the slope protection dam can be pre-constructed as a slope protection dam project of a river channel, can effectively protect two banks of the river channel in a water-rich period and a flood period, and is constructed in a manner that flood control modules are connected together in a flexible manner; the flood control module is a 900x900x600mm cube, vacuum connecting grooves (7) on the rubber outer surface layer (5) on the outer surface of the module are connected with vacuum connecting grooves of other modules, and the flood control module is connected together through air pressure, so that firm and inseparable connection between the modules can be ensured.
3. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: after the slope protection wall is constructed, the slope protection wall is integrally hoisted to a designated area, when a rich water period comes, a water suction port (2) of the slope protection flood protection wall is started, and water flow facing to a water facing surface (6) is sucked into the device for storage; the inside cavity water storage space that is of this device can alleviate the probably harm that the river course rises water and produces low reaches and both sides when flood invasion and attack.
4. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: flood control module internally mounted has water pump (12), will be for holistic module wall body water absorption drainage provides power, after every module is inside to be stored quantitative water, whole flood control wall's weight will increase, holistic stability will improve.
5. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: the module base ann has fixed drill bit device (8), adopts the mode of hydraulic pressure bloated bolt through to water injection in the connecting rod for fixing device carries out fixing device to the submarine drilling of place river course, and after the flood control module of flood control bank protection wall body bottom row accomplished fixed work, all fixed drill bit devices all bored about the river bottom 1.5-2m, guaranteed the stability of flood control wall body.
6. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: each flood control module is constructed by three materials, namely rubber, a microcrystalline foamed ceramic material and a steel plate, and has good wear resistance, water erosion resistance and impact resistance; when the whole slope protection embankment dam wall is constructed, the vacuum suction pump (14) in the module extracts and pumps air in the module joint, and the whole slope protection embankment is stably seated on the slope of the appointed river channel for a long time.
7. A method for constructing a new fast-assembling permanent dam as claimed in claim 1, wherein: when the flood control module needs to be disassembled and replaced, only the movable upper panel (7) of the module needs to be opened, and the module joint is inflated through the vacuum pump, so that the vacuum environment at the module joint disappears, and the module can be naturally loosened and disassembled.
Background
At present, slope protection projects aiming at two banks of a river channel in China are mainly used for protecting gardens and towns at the two banks from being invaded by flood, and the main construction positions of river banks are all on soft soil layers of the river banks, so that the overall stability of the dam is insufficient; meanwhile, the river levee is mainly made of sandstone which is poured by cement, and the dam is integrally impacted and hollowed by water flow with larger flow.
Disclosure of Invention
According to the novel construction method of the fast-assembly permanent dam, the fast-assembly flood control modules are used for splicing the integral slope protection and flood control walls, the operation is simple, the time and the labor are saved, the advantages of the anti-seismic wear-resistant materials can be fully exerted after the construction, and the scouring and damage of flood disasters to the river banks can be firmly resisted.
Drawings
Fig. 1 is a front view of the present slope protection embankment wall.
Figure 2 is a sectional view of a single flood protection building module.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Fig. 1 is a front view of the slope protection embankment wall, which includes a flood protection building module (1), a water suction port (2), a water discharge port (3), a module splicing part (4), a rubber outer surface layer (5), a water facing surface (6), a vacuum connection groove (7), and the like.
Please refer to fig. 2, which is a sectional view of a single flood protection building module, comprising a movable top panel (7), a fixed drill device (8), a water pipeline (9), a pressure detection pipeline (10), a tee joint (11), a water pump (12), a valve (13), a vacuum suction pump (14), etc.